rendering of Story Road EBRC station
Annual Public Hearing of the Citizens Watchdog Committee (CWC) for the 2000 Measure A Transit Sales Tax Program
04/26/2023

The Citizen’s Watchdog Committee (CWC) invites you to provide your input on 2000 Measure A expenditures, including the results of the annual compliance audit for Fiscal Year (FY) 2022.

Join us at the annual public hearing:

Wednesday, May 10, 2023 at 5:30 p.m. (time certain)

In Person: VTA Headquarters, 3331 North First Street, San Jose, CA 95134 - Conference Room B-106

Via Zoom: https://us02web.zoom.us/j/87207700818 Webinar ID: 872 0770 0818

Contact the Office of the Board Secretary at (408) 321-5680 or email board.secretary@vta.org for questions or to confirm the meeting date, time, and location. Sign language and interpreter services will be provided upon request by contacting the Board Office at least five days prior to the meeting. Written comments are accepted until 10:00 a.m. on May 10 by email.

The Audit Results are In!

The Committee commissioned an audit of the Measure A Program financial records and schedule for FY 2022 (July 1, 2021 - June 30, 2022). Crowe LLP, an independent certified public accounting firm, conducted the compliance audit and issued an unqualified (“clean”) opinion, indicating that VTA complied, in all material respects, with the requirements for the measure. This is the 17th consecutive audit receiving a clean opinion.

The Audit results are available on VTA’s website at www.vta.org/cwc-fy22audit and at the VTA Administrative Office at 3331 North First Street, San Jose, CA 95134 in the Building B Main Lobby. You can also access the CWC agenda packets here www.bit.ly/vta-cac-cwc-agendas.

Here's the Back Story!

In November 2000, Santa Clara County voters approved Measure A, a half-cent sales tax for specific public transit capital improvement projects and operations. Revenue collection began in April 2006. Highlights for FY 2022 include key activities for VTA’s BART Silicon Valley Extension project, Eastridge to BART Regional Connector project, and Caltrain Electrification efforts.