Starting this spring, VTA will be repairing or replacing worn elements of the light rail overhead catenary system (OCS) and performing other necessary work to keep VTA’s light rail system in a state of good repair. As a result, segments of the light rail lines will be closed for construction periodically from late April through late summer which may result in transit impacts to your daily commute or visits to popular events and attractions this summer.
Light rail service in areas impacted by this construction will be replaced by bus service or a “bus bridge” to ensure passengers can still travel to their destinations. Riders are highly encouraged to plan their trip in advance.
Below is a tentative schedule* of upcoming transit impacts. Details are subject to change.
Dates |
Light Rail Stations Closed |
Light Rail Lines Impacted |
Bus Bridge |
---|---|---|---|
April 24-28 |
Mountain View ↔️ Moffett Park |
Orange |
Mountain View ↔️ Lockheed Martin |
May 10-12 |
Winchester ↔Hamilton
|
Green |
Winchester ↔ Bascom |
May 22-June 8 |
Ohlone/Chynoweth ↔ Curtner
|
Blue |
Blossom Hill ↔ Tamien |
June 12-July 1 |
Santa Teresa ↔ Branham |
Blue |
Santa Teresa ↔ Capitol |
July 7-14 |
Blue: Convention Center ↔ Curtner
Green: Convention Center |
Blue, Green |
Blue: San Antonio ↔ Capitol
Green: San Antonio ↔ San Fernando |
July 18-23 |
Borregas ↔ Champion |
Orange |
Lockheed Martin ↔ Baypointe |
July 28-August 4 |
Blue: Tasman ↔ Gish
Green: TBD |
Blue, Green |
Blue/Green: Civic Center ↔ Baypointe |
August 7-13 |
Blue: Tasman ↔ Orchard
Green: TBD
Orange: Great America ↔ Cisco Way |
Blue, Green, Orange |
Blue/Green: Bonaventura ↔ Baypointe
Orange: Old Ironsides ↔ Alder |
*For the most current and updated information, including the schedule throughout summer 2024, please visit the Light Rail Rehab page. Riders can also subscribe to Service Alerts to receive notifications about affected routes.