VTA's BART Silicon Valley Phase I

Phase I of VTA’s BART Silicon Valley Program begins south of BART's Warm Springs Station in Fremont, proceeds through Milpitas and ends in the Berryessa area of north San José. Phase II is the last six miles and includes four stations.

Phase I includes two new BART stations that are each part of two bigger, new transit centers: the Milpitas Transit Center and the Berryessa Transit Center. Both Transit Centers feature:

The Milpitas Transit Center also includes a direct

Phase I of VTA’s BART Silicon Valley Program begins south of BART's Warm Springs Station in Fremont, proceeds through Milpitas and ends in the Berryessa area of north San José. Phase II is the last six miles and includes four stations.

Phase I includes two new BART stations that are each part of two bigger, new transit centers: the Milpitas Transit Center and the Berryessa Transit Center. Both Transit Centers feature:

The Milpitas Transit Center also includes a direct connection to VTA’s Milpitas Light Rail Station (formerly known as the Montague Light Rail Station). More on the features of the Milpitas Transit Center.

The Berryessa Transit Center features rapid bus service to and from downtown San José. Learn more about the Berryessa Transit Center's features.

Below, we have answers to a few basic questions about BART service to/from the Milpitas BART Station & the Berryessa/North San José BART Station. For more information on BART service, including the cost between every station, schedule of trains, and location of stations, please visit the BART website or contact BART.

 

Timeline

Title
Study Development
Phase Date Range
-
Title
Alternatives Analysis
Phase Date Range
-
Title
VTA Board adopted Major Investment Study
Milestone Date
Title
Environmental Clearance
Phase Date Range
-
Title
VTA Board Certified Final Environmental Impact Report
Milestone Date
Title
VTA Board Certified Final Supplemental Environmental Impact Report
Milestone Date
Title
VTA Board Separated Project into Two Phases
Milestone Date
Body

The VTA Board of Directors committed to separate the BART project in two overlapping phases - Phase I and Phase II. Phase I would be completed first. Phase I became the first 10 miles from Fremont to Berryessa and Phase II became the final 6 miles through downtown San Jose into Santa Clara.

Title
VTA Board Certified Final 2nd Supplemental Environmental Impact Report
Milestone Date
Title
Design and Engineering
Phase Date Range
-
Title
Construction
Phase Date Range
-
Title
Testing
Phase Date Range
-
Title
VTA transferred control of the BART trackway, systems & facilities to BART
Milestone Date
Body

VTA's BART Silicon Valley Berryessa Extension Project achieved another major milestone when VTA transferred control of the BART trackway, systems and facilities to BART.

BART now has exclusive access to begin the final phase of testing and pre-revenue operations in preparation for passenger service at both the Milpitas & Berryessa Transit Centers. 

Title
Open for Passenger Service
Milestone Date
Body
VTA’s Berryessa Transit Center Honored for Commitment to Sustainability
Milestone Date
VTA’s Berryessa Transit Center has been awarded the Envision Platinum Award by The Institute for Sustainable Infrastructure’s (ISI) awards program. The Envision Platinum award recognizes the...

Total Funding

$2.3 billion